Short answer
Quoted per pavilion. For country pavilions, total area and number of co-exhibitors, scope (design, build, AV, furniture, logistics, manpower, hospitality) and number of cities or shows in the programme do most of the work in the arithmetic. Decide those before you brief anyone, insist on an itemised quote, and compare like with like: the cheapest total is usually the one with the most left out.
Key takeaways
- Only 48% of this page's illustrative total is fabrication. The other ₹3,49,000 is everything a lump sum hides.
- Reuse beats negotiation. A second outing with the same structure is 32% of the first show's figure, with nothing haggled.
- Spend longer at concept stage than feels comfortable. It is the only point at which a change costs nothing but time.
- Quoted per pavilion.
- Two things dominate the quote: total area and number of co-exhibitors and scope (design, build, AV, furniture, logistics, manpower, hospitality).
- Six ordinary substitutions explain 22% of the gap between two quotes for the same brief. Ask for the itemisation and the gap stops being a mystery.
Country pavilions: the published ranges
We build national pavilions for foreign governments exhibiting in India and Indian pavilions at overseas trade fairs.
Quoted per pavilion. Expect a modest premium in Delhi NCR, Mumbai and Bengaluru, driven by venue labour rules and compressed build-up windows rather than by the build itself. A Tier 2 city planned four weeks out is frequently the cheapest version of the same stand.
Custom fabrication is published at ₹9,000–₹18,000 per sq.m. Below that sit system builds, where the frame is reused instead of cut fresh, and below those an upgraded shell scheme. Read those as three different bargains rather than three qualities: you are trading how bespoke the stand looks against how much of it you still own after the show.
Note the span: top of band to bottom of band is a factor of 2, exactly. That makes the first real budget question not "how much" but "which" — the same build money is a stand of a given area at a plain finish, or half that area at a premium one. Decide that before the concept, because it changes the layout, not just the specification.
| Construction type | Relative cost | What you keep afterwards |
|---|---|---|
| Shell scheme upgrade | Lowest | Graphics only |
| Octanorm / system build | Low | Frame and graphics |
| Modular with custom graphics | Medium | Frame, graphics, furniture |
| Custom wooden build | ₹9,000–₹18,000/sq.m | Limited |
| Double-decker | Quoted per project | Structure, with engineering |
Reuse is the column that decides cost over a year of shows, rather than cost at this one. Read it before the cost column if you exhibit more than twice.
What actually moves a country pavilions price
A quote is not a number, it is a set of decisions you have already made without realising it. These are the variables doing the work, and each one is negotiable before the brief goes out and expensive afterwards.
Area and open sides dominate everything else. A stand with three open sides needs three finished faces, three lighting runs and more staff than an inline stand of the same area, so it costs more per square metre even before any design decision is made.
Then there is the pair nobody prices at briefing stage: lead time and finish level. 4 weeks is the schedule for 36 sq.m — take that away and you have not saved anything, you have bought the same work on an overtime shift. Finish is the other one: specify veneer where laminate would read identically from the aisle and you have spent the lighting budget on something visitors cannot see.
- Approval layers with organisers, embassies or departments
- Total area and number of co-exhibitors
- Scope (design, build, AV, furniture, logistics, manpower, hospitality)
- Number of cities or shows in the programme
- The finish on surfaces visitors can touch, as against the ones they cannot
- Whether furniture is hired for the week or fabricated to keep
- The number of approval rounds before the drawing is frozen
- How much of the stand has to be new, and how much can come out of storage
You cannot compare two quotes until both describe the same stand.
The lines a quote has to name
An itemised quote is not a courtesy, it is the only format in which a price can be checked. Each line is something you can question, reduce or delete; a single figure is something you can only accept or refuse.
Four lines go missing more often than the rest: the return journey, the on-site crew, the dismantle, and the tax. On this page's illustrative 36 sq.m figures, transport and installation alone are ₹1,17,000 — which is what a quote without them is quietly saving.
For turnkey participations there are a few lines beyond the obvious ones that belong on the page: the certification the venue will ask for, the drawings the organiser will ask for, and the person whose phone you will be ringing at seven in the morning on build-up day. None of those are large figures. All of them are expensive to arrange late.
- Multi-booth coordination
- VIP and delegation areas
- Night-shift or overtime labour, if the build-up window forces it
- Graphics proofing, and what happens if a panel has to be reprinted
- Storage of reusable elements after the show, and for how long
- Installation, the on-site crew, and who supervises them
- Pre-build or dry assembly at the workshop before dispatch
- Organiser drawing submission and approval handling
- Cultural design language
- Embassy and organiser liaison
Thirty-six square metres, costed properly
Work one example through properly and the subject becomes concrete. Below is 36 sq.m of custom build: the structure at ₹9,000 per sq.m — the lower end of the published band — and then each of the scopes that a single figure would have hidden.
At ₹6,73,000 this stand works out at roughly ₹18,694 per sq.m all-in, which is the number worth comparing between vendors. Note how much of it is not the stand: graphics, lighting, flooring, furniture, transport and crew together come to ₹3,49,000, a little more than the fabrication itself.
Before you use that number, apply two adjustments. The structure is priced at the band's lower end, so a heavier finish specification pushes it toward ₹6,48,000 for the same 36 sq.m. And the total is before GST throughout. With both adjustments made, it is a sound planning figure for a mid-finish custom stand, and nothing more than that.
| Structure and joinery (36 sq.m × ₹9,000) | ₹3,24,000 |
|---|---|
| Raised flooring and carpet | ₹43,000 |
| Furniture — counters, seating, planters | ₹38,000 |
| Graphics — brand wall, tensioned fabric and vinyl | ₹97,000 |
| Lighting — track, aimed spots and backlit panels | ₹54,000 |
| Transport, both ways | ₹52,000 |
| Installation, crew and dismantle | ₹65,000 |
| Indicative total, before GST | ₹6,73,000 |
Illustrative only, using the published ₹9,000–₹18,000 per sq.m band at its lower end for the structure line. The remaining lines are planning figures rather than a quotation, and your own will differ with finish level, city, venue rules and how much AV you add. GST is extra. Space rental, power, badges, travel and your own team's time are not in this figure — they are invoiced by the organiser or by nobody at all.
Area against finish: what the band actually means
The band is a range, not a price, and its two ends buy very different stands. At any given size, the lower figure is the plain version and the upper is the premium one — and because the upper is twice the lower, the premium version of a stand costs the same as the plain version of twice the area. Here is that worked out at common sizes.
Hold the two middle columns next to each other and the trade is exact: the difference between them, ₹9,000 per sq.m, is the same as the lower rate itself. Upgrade the finish or double the footprint — at the published band, those two cost the same. Few budget decisions are this clean, and almost nobody uses it.
The honest rule is that area serves activity and finish serves belief. Demonstrations, queues, meetings and products that must be touched all need floor, and no amount of veneer compensates for a stand people cannot get into. A launch, a new category entry, or a brand that has to look established needs finish, and does better with a smaller, denser, well-lit stand than with a larger plain one.
| Stall size | Build at ₹9,000/sq.m | Build at ₹18,000/sq.m | What the difference buys |
|---|---|---|---|
| 9 sq.m | ₹81,000 | ₹1,62,000 | Better print, aimed light instead of clip lamps, and an edge finish that survives the week |
| 12 sq.m | ₹1,08,000 | ₹2,16,000 | A laminate that survives handling, a lighting track, and a counter that locks |
| 18 sq.m | ₹1,62,000 | ₹3,24,000 | A raised floor, aimed lighting and furniture you do not have to apologise for |
| 36 sq.m | ₹3,24,000 | ₹6,48,000 | Veneer or PU paint in place of laminate, backlit panels and a screened meeting corner |
| 72 sq.m | ₹6,48,000 | ₹12,96,000 | Architectural form — curves, a ceiling element, and a stand that reads as a building |
Both columns are build only, at the two ends of the published band. Read them as the first line of a quote rather than as a quote.
Why two quotes for one brief differ
The question we are asked most often is why one vendor has quoted substantially less than another for what looks like the same stand. The answer is almost never margin. It is that the two quotes describe two different stands, and the brief was not specific enough to prevent that.
Here is the gap itemised, on the same illustrative 36 sq.m stand. Six ordinary substitutions — none of them dishonest, all of them things a vendor might assume — take ₹6,73,000 down to ₹5,23,000. That is ₹1,50,000, or 22% of the total, without anybody quoting a different margin or a different standard of workmanship.
The remedy is unglamorous. Write the specification yourself — board, graphics medium, number of fixtures, flooring type, furniture list, crew and shift — and send the same page to everybody. The prices that come back will be close together, and you will be choosing a vendor rather than guessing at a scope.
| Line that differs | Why the two figures are not the same | The question that settles it |
|---|---|---|
| Taxes | One total is before tax and the other after it | Give me both the pre-tax and the post-tax figure |
| Graphics | Tensioned fabric on a frame against printed flex taped to a panel | What is it printed on, and how is it fixed to the wall? |
| Structure | Ply and MDF to a finished edge in one quote, a lighter board with an exposed edge in the other | Name the board, the thickness and the edge finish |
| Furniture | Hired against fabricated, and a four-piece package against an eight-piece one | List the pieces, and say which are hired and which are built |
| Lighting | Fourteen aimed fixtures against six, or against none at all | How many fixtures, of what type, aimed at what? |
| Installation | A day crew against a night-shift crew, with or without supervision | How many crew, on which shift, and who supervises them? |
| Electrical | The organiser's power charge, the stand's own wiring, or neither | Who pays the organiser, and who wires the stand? |
| Transport | One leg, both legs, or quietly left out | Is the return journey inside this figure? |
Every row is a question you can ask both vendors in the same email. The answers, side by side, usually explain the entire difference.
| Printed flex taped to panels instead of tensioned fabric on a frame | ₹26,000 |
|---|---|
| Six aimed spots instead of fourteen, and no backlit panel | ₹18,000 |
| Carpet laid straight on the hall floor instead of a raised platform with cable management | ₹21,000 |
| A four-piece hired furniture package instead of eight pieces | ₹12,000 |
| Installation and dismantle left as "to be advised" | ₹31,000 |
| Lighter board in the structure, with an exposed edge instead of a finished one | ₹42,000 |
| Total difference between the two quotes | ₹1,50,000 |
Illustrative, built by making six substitutions to the 36 sq.m example above. The higher quote is ₹6,73,000 and the lower is ₹5,23,000; the difference is ₹1,50,000, 22% of the higher figure. None of these substitutions is dishonest — each is a decision the brief failed to make — and none of them is visible unless both quotes are itemised. Figures are planning numbers, not a quotation, and GST is extra on both.
Where to cut, and where cutting costs more
Not every line in a quote is load-bearing, and not every cheap line is optional. The distinction is worth learning properly, because the expensive mistakes in exhibiting are almost all deletions that came back — on the first morning, in the organiser's window, at somebody else's rates.
Apply a single test to every candidate for deletion: if it is missing, who handles it and where? Anything that ends up being handled at the venue has not been saved. Site is the most expensive place on earth to buy a sheet of board, an electrician's hour or a reprint.
Below: the real options as a list, then the false economies as a table. Read the list first if you are over budget, because the savings in it are larger and none of them will be visible from the aisle.
- Backlighting on every panel, rather than on the one panel you want looked at
- A printed floor, when plain carpet in the brand colour does the same job
- A ceiling or hanging element, unless the stand has to be found from across the hall
- Veneer or PU paint where a good laminate reads identically from the aisle
- Giveaways in quantity, which measure footfall rather than interest
- Working shutters and locks on storage that nobody will see
| Line item | Why it reads as padding | The consequence |
|---|---|---|
| Raised flooring | Carpet on the hall floor costs less | The cables then run under the carpet, and every visitor finds them with their feet |
| A single project manager | Each vendor manages themselves | Then every gap between vendors is yours to discover, usually at eight o'clock on the first morning |
| The cable and socket count on the drawing | That is site detail | Site detail becomes a visible extension lead across the floor of a stand you paid to look expensive |
| A graphics proofing round | The artwork is final | Large-format print is where a wrong size and a missing bleed turn into a full reprint of the hero wall |
| Packing crates and transport cover | It travelled fine last time | Once is not a plan. A cracked acrylic panel is a reprint, a lorry and a lost day |
| One spare panel for the hero wall | It will be fine | A scuffed hero panel is the one thing every photograph of the stand will show |
| Storage between shows | We will decide after this one | "After this one" is a fortnight of the structure stacked in a corner, which is where reusable elements stop being reusable |
If the budget genuinely will not stretch, cut from the list below this table instead. These lines are the ones that cost more when they are missing.
The venue is the most expensive shop in India, and it only opens when you have run out of time.
The price of a late decision
Changes are where budgets actually overrun, and they do not appear on any quote. What makes them expensive is timing rather than magnitude: moving an entrance is a conversation at concept stage, a redraw after sign-off, a rebuild in production, and an improvisation at the venue.
So the cheapest thing you can buy is time at the front. A 36 sq.m build runs to 4 weeks on our schedule — 3 weeks base plus 1 for the area — and a premium finish or a double-decker element adds 2 and 2 weeks respectively. None of that window is spare, which is exactly why a decision taken in week one is free and the same decision in week four is not.
Protect yourself with two things. First, a single named approver — two people with different opinions about the same wall is the most expensive organisational arrangement in exhibiting. Second, a written variation process, so that every change has a price attached at the moment it is agreed rather than at the moment it is invoiced.
| Point in the programme | Cost of a change here | The reason |
|---|---|---|
| While the concept is being designed | Time, and nothing else | Nothing has been drawn to scale, priced, cut or ordered. This is the only stage where changing your mind is free, which is the argument for spending longer in it |
| After design sign-off, before production | A redraw and a requote | Drawings have gone to the organiser and materials have been priced against them. Both have to be done again, and the organiser's queue does not restart for you |
| After materials are ordered | The material, plus its replacement | Board, laminate and print are bought to a cutting list. A changed dimension turns the ordered sheet into offcuts |
| After graphics go to print | A full reprint of the affected panel | Large-format print has no partial fix. A logo at the wrong size is a new panel, not an amendment |
| After dispatch | Freight both ways, and a hole in the build schedule | The panel is on a lorry. The alternative is a modification on site, with the wrong tools and an audience |
| During build-up | Night-shift labour, and whatever can be improvised | There is no workshop at the venue, no spare material, and the clock belongs to the organiser rather than to you |
Read the first row twice. It is the only stage at which a change is free, and it is the stage exhibitors rush through fastest.
Exhibiting soon? Let's build your stall.
If the total is fixed, start there
In practice the budget usually exists before the brief. That is not a problem; it is a better starting point, provided you do the subtraction first. The step that gets skipped is taking out the exhibiting costs that never appear on a stall quote at all, because those are the ones that arrive late and unbudgeted.
What follows is the list of costs no stand builder will quote you, and then one way to split a total, shown against ₹10,00,000. Treat it as an illustration and not as a benchmark — there is no published standard and we are not inventing one. Its useful feature is the last two lines: ₹9,00,000 is what a builder quotes against, ₹1,00,000 is yours alone, and ₹50,000 of the total is held back rather than committed.
The build line comes to ₹4,50,000, which buys 50 sq.m of structure at the bottom of the published band and 25 sq.m at the top. Hold that against the stall you have booked. If the booked area is larger than 50 sq.m, the arithmetic is telling you to use a system build rather than a custom one, and it is telling you now rather than in week three.
- Promoters, hostesses or interpreters, if your visitors need them
- Product freight — the goods on display travel separately from the stand that holds them
- Storage of reusable elements between this edition and the next
- Space rental, invoiced to you by the organiser rather than by your stand builder
- The organiser's power connection, charged against the load you declare
- Hospitality: tea, coffee, water, and whatever the meeting corner is going to serve
- Exhibitor badges, extra passes and vehicle parking
- Lead-capture devices, the data connection, and somewhere to charge them
| Allocation | Share | Illustrative amount |
|---|---|---|
| Stand build — structure, joinery and finish | 45% | ₹4,50,000 |
| Graphics, lighting and AV | 20% | ₹2,00,000 |
| Flooring and furniture | 10% | ₹1,00,000 |
| Transport, installation and dismantle | 15% | ₹1,50,000 |
| Your own show costs — travel, staffing, collateral, hospitality | 5% | ₹50,000 |
| Contingency, held back rather than allocated at briefing | 5% | ₹50,000 |
Illustrative only. There is no published standard split and this is not offered as one — it is a planning habit, shown with the arithmetic visible so you can substitute your own shares. The shares are whole percentages summing to 100, so the amounts total exactly ₹10,00,000. The first four rows, ₹9,00,000, are what a stand builder quotes against. GST sits on top.
Size, space and what fits inside it
Before comparing prices per square metre, look at what a square metre does. Our planner's ratios are simple: storage at 10% up to 18 sq.m and 15% beyond it, a default 5% for a meeting corner, and the balance as display. Apply them and most stall-size arguments resolve themselves.
Read the visitor column as a constraint rather than as information. It is display area divided by 2.5, and if your footfall expectation implies more people in the stand at once than that, the thing standing in the way is the floor plan, not the campaign.
The build-weeks column is a budget column in disguise. Our schedule is 3 weeks base, +1 from 24 sq.m, +2 from 54 sq.m, +2 for a premium finish and +2 for a double-decker. Compressing it does not reduce the work; it relocates the work to night shifts and rush rates.
| Area booked | Display | Storage | Staff | Visitors at once | Lead time |
|---|---|---|---|---|---|
| 9 sq.m | 7.6 sq.m | 0.9 sq.m | 2 | 3 | 3 |
| 18 sq.m | 15.3 sq.m | 1.8 sq.m | 2 | 6 | 3 |
| 36 sq.m | 28.8 sq.m | 5.4 sq.m | 4 | 11 | 4 |
| 54 sq.m | 43.2 sq.m | 8.1 sq.m | 6 | 17 | 5 |
| 72 sq.m | 57.6 sq.m | 10.8 sq.m | 8 | 23 | 5 |
| 100 sq.m | 80 sq.m | 15 sq.m | 12 | 32 | 5 |
Staff = area ÷ 9, minimum 2. Visitors = display ÷ 2.5, minimum 3. Lead time is 3 weeks base, +1 from 24 sq.m and +2 from 54 sq.m.
Paying for it: stages and deliverables
Payment terms vary by vendor, by scope and by how long the two of you have worked together, and we are not going to invent a standard split — there is no honest source for one. What can be said without inventing anything is what each stage ought to correspond to, and that is the part worth negotiating.
The principle is that a payment stage should correspond to a deliverable rather than to a date. Approved drawings exist or they do not. Materials are on the shop floor or they are not. A pre-build can be walked around or it cannot. The stand is standing at the venue or it is not. Each of those is checkable; "end of week two" is not.
The item to settle alongside the schedule is how changes get priced. Who approves them on your side, in what format, and is the figure confirmed before work starts? Nearly every uncomfortable conversation about an exhibition invoice began as a change that nobody priced at the moment it was agreed.
01
Ask for the schedule inside the quote
Payment terms belong in the same document as the itemised scope, not in a separate message afterwards. If the stages and the deliverables are written on one page, you can see whether they line up — and if they do not, that is a conversation to have before you sign rather than in week three.
02
Tie every stage to something you can see
A milestone should correspond to a deliverable you can check with your own eyes: approved drawings, materials on the shop floor, a pre-build you can walk around, the stand standing complete at the venue. A date in a calendar is not a milestone, because a date arrives whether or not the work did.
03
Name one approver on your side
One person signs the drawing, the finish schedule and every variation. Two approvers with different opinions is the most expensive organisational structure in exhibiting, because the cost of resolving them lands in production.
04
Keep the organiser's bills on a separate line
Space rental, your power connection and your badges are invoiced by the organiser, not by the stand builder. Keep them in a different part of your own budget, so that stand quotes are only ever compared with stand quotes.
05
Ask what happens if the show moves
Editions get postponed and dates shift. Ask what is recoverable and what is not if that happens, and at which stage the answer changes — the honest answer is different before materials are ordered and after a wall has been built.
06
Write the variation process down before there is a variation
Agree who on your side can approve a change, in what format, and whether the price of that change is confirmed before the work starts. Most budget overruns are not one large surprise; they are six small changes that nobody priced at the moment they were agreed.
A milestone with no deliverable attached is a date, and a date is not a milestone.
Reuse arithmetic: the second show is the cheap one
The arithmetic changes completely once you exhibit twice. Costing a stand against one show, when it will stand at three, overstates it by a wide margin; but it only overstates it if the stand was built to be reused, which is a decision made at design stage and cannot be made afterwards.
The second outing is costed in full in the example on this page. The structure, having been stored, does not reappear: what remains is a graphics reprint for the new message, refurbishment of what got marked, storage between the two shows, and the same transport and installation as before. That comes to ₹2,15,000 against the first show's ₹6,73,000 — 32% of it — because ₹4,58,000 of the first build is not bought a second time.
Extended to a third show in the table, the average per show becomes about ₹3,67,667, against ₹6,73,000 for the first outing alone: a 45% fall. No negotiation produces that. It comes entirely from a design decision taken before the first panel was cut, which is why it has to be asked for at briefing stage.
Three conditions have to hold, and they are all specification rather than luck. The structure has to be modular, dismantled in panels rather than broken down. The graphics have to be a separate layer — fabric on a frame, reprinted rather than rebuilt. And somewhere has to store it, which is a real cost and appears as a line in the example rather than being quietly ignored.
| Edition | Cost of this one | Total so far | Average per show |
|---|---|---|---|
| Show 1 — the first build | ₹6,73,000 | ₹6,73,000 | ₹6,73,000 |
| Show 2 — same structure, new graphics | ₹2,15,000 | ₹8,88,000 | ₹4,44,000 |
| Show 3 — same structure, new graphics | ₹2,15,000 | ₹11,03,000 | ₹3,67,667 |
Illustrative, built from the two worked examples on this page: ₹6,73,000 for the first build and ₹2,15,000 for each subsequent outing with the same structure. The average is the cumulative figure divided by the number of shows, rounded. It assumes the stand is stored and reused rather than rebuilt, and that each show carries its own transport and installation — which it does.
| Graphics reprinted for the new show and the new message | ₹48,000 |
|---|---|
| Refurbishment — replaced panels, touch-up paint, relaminating what is marked | ₹32,000 |
| Storage of the structure between the two shows | ₹18,000 |
| Transport, both ways | ₹52,000 |
| Installation, crew and dismantle | ₹65,000 |
| Indicative second-show total, before GST | ₹2,15,000 |
Illustrative, and dependent on the first stand having been specified as modular. There is no structure line because the structure already exists; the refurbishment line is what a stored stand typically needs rather than a fixed figure. Against the first show's ₹6,73,000, this is 32%, so ₹4,58,000 of the original build is not purchased again. GST is extra. Space rental, power and badges are the organiser's invoices and appear in neither figure.
Where to save, and where the saving shows
Budget by sightline. What faces the aisle deserves the spend; storage walls, back-of-house and anything above head height does not, because nobody is looking at it.
Three habits cut more than any negotiation does — reuse the frame, hire rather than build the furniture, and keep graphics on fabric so next year's edition costs a reprint instead of a rebuild.
What not to cut is lighting. Hall lighting is designed for circulation, not for your product, so an unlit stand reads as under-funded no matter what the joinery cost. It is the cheapest line with the largest visible effect.
The savings that work are the ones decided early. Booking inside the lead time, redesigning after sign-off and adding scope in production are not savings at all — they are the three most reliable ways to spend more than you planned. Every item in the list below has to be chosen before the brief is frozen to be worth anything.
- Print one hero graphic properly and keep everything around it plain
- Share a lorry with your own product freight, if the dates allow it
- Keep the footprint simple — every curve, angle and radius is another line on the cutting list
- Hire the AV for the week instead of buying a screen you will then have to store
- Keep graphics on fabric, so the next edition is a reprint instead of a rebuild
- Choose a laminate that reads like veneer from a metre away, and spend the difference on light
- Book early: rush charges and night-shift labour are avoidable rather than inevitable
What goes wrong with country pavilions quotes
Three things go wrong often enough to be predictable, and all three are settled before anybody builds anything. The first: too many vendors with no single point of accountability. It reads as a quality failure and it is really a specification one — ask what the quote names, and who will physically do the work, before comparing totals.
Next comes scope nobody wrote down — the single commonest cause of a quote that grows. Finish, fixture count, flooring type and furniture list: unnamed, each of them is an assumption, and the assumption will be resolved in the vendor's favour because you did not make it yourself.
The third failure is a budget that was correct when it was written. Scope added in ones and twos after sign-off does not announce itself as an overrun until the final invoice, which is exactly why the change procedure matters as much as the price.
- Budget overruns from scope that was never itemised
- Delayed approvals that compress build-up time
- Too many vendors with no single point of accountability
- Inconsistent branding across co-exhibitor booths
Get an accurate price
Send the show name, city and dates, the area you have booked, how many sides are open, and a couple of reference images. That is a complete brief for pricing purposes, and it produces a concept and an itemised country pavilions quote within about two days.
We design free with every confirmed fabrication order, fabricate in our own workshops, prepare the organiser drawings and approvals, and put one project manager on the job from brief to dismantle. Quoted per pavilion.
Before you sign anything, get three answers in writing: what is itemised, what is excluded, and what happens to the price when the drawing changes. They take one email to request, and they are the difference between a quote and a guess.
Frequently asked questions
Why do two quotes for the same brief differ so much?+
Almost always because they describe two different stands. On the illustrative 36 sq.m figures on this page, six substitutions — board, graphics medium, fixture count, flooring, furniture package and installation — account for ₹1,50,000, or 22% of ₹6,73,000. Ask both vendors to itemise against the same written scope and the gap explains itself.
Does reusing a stand really lower the cost?+
Directly, and more than negotiation does. On this page's illustrative figures a second outing with the same structure carries ₹2,15,000 rather than ₹6,73,000 — 32% of the first show — because ₹4,58,000 of the first build is not bought again. Across three shows the average falls to about ₹3,67,667.
How much contingency should I hold back?+
Enough to absorb one change you have not thought of yet. The illustrative allocation on this page holds back ₹50,000 of ₹10,00,000, which is a planning habit rather than a published rule — set your own figure, but set it before briefing, because a contingency invented afterwards is just an overrun.
When is payment due?+
Terms are agreed in the quote. Ask for the schedule in writing alongside the itemised scope, and check that each stage corresponds to something you can see — approved drawings, materials on the floor, a pre-build, the finished stand — rather than only to a date.
How far ahead should I book to avoid rush costs?+
Our own lead times are 3 weeks for a small stall, 4 from 24 sq.m and 5 from 54 sq.m, with another 2 for a premium finish and 2 for a double-decker. Work backwards from the build-up date and add your own approval rounds — those, not fabrication, are what usually makes a job late and therefore expensive.
Do you charge separately for design?+
3D design is free with every confirmed fabrication order, and revised until you approve it. Design-only projects are quoted per stall.
Does a bigger stand cost proportionally more?+
The build line scales with area at the published band — 50 sq.m of structure at ₹9,000 per sq.m is ₹4,50,000, and the same money buys 25 sq.m at ₹18,000. The lines that do not scale in a straight line are transport, crew and supervision, so ask your builder which of your lines move with area and which are closer to fixed.
What does a 36 sq.m stand cost?+
Using the published band, the structure alone is ₹3,24,000–₹6,48,000. Add graphics, lighting, flooring, furniture, transport and installation and the illustrative all-in figure on this page is ₹6,73,000 before GST — about ₹18,694 per sq.m — for a mid-finish custom stand.
How can I lower the cost without the stand looking cheap?+
Book early so no part of the job is paid at rush rates, reuse a modular frame, hire furniture rather than building it, keep graphics on fabric so the next edition is a reprint, and spend the saving on light. Lighting is the smallest significant line on a quote and the one with the largest visible effect.