By the Exhibition Stall Design editorial team · Updated 1 October 2026 · 9 min read
Short answer
From first enquiry to an empty hall, an event management company project has ten stages: brief, concept, two revision rounds, design freeze with an itemised quote, organiser submission, production, dry build and dispatch, build-up and handover, show-day support, then strike and clearance. Lead time follows a formula — 3 weeks base, +1 from 24 sq.m, +2 from 54 sq.m, +2 for a premium finish, +2 for a double-decker — so you can check a promised date against arithmetic.
Key takeaways
- Lead time is 3 weeks for a stall under 24 sq.m, 4 weeks from 24 sq.m and 5 weeks from 54 sq.m, plus 2 weeks for a premium finish and 2 more for a double-decker.
- Your approval is on the drawing set and the materials schedule, not on the render. The render is the sales tool; the drawing is what anyone can be held to.
- A day lost before design freeze is a day you can still spend. A day lost after it comes out of finishing, quality control or build-up.
- Dismantle is part of the job, not an afterthought. Clearing the stand inside the organiser's window is what protects your deposit.
- The workshop owns 11 of the 28 days on a 36 sq.m build. The rest is decisions, drawings, approvals, freight and installation.
- Ask for a written storage inventory after the show. It is the document that makes the second edition cost a fraction of the first.
The shape of an event management company project, on one screen
One accountable team plans, designs, builds and runs your event — venue, stage, AV, branding, logistics, guest flow and show-calling — so you only focus on your guests.
Most first-time exhibitors assume the hard part is the design. It is not. The hard part is a sequence of handovers between you, the supplier, the organiser and the venue, each with a date attached, any one of which can push the others. Large exhibitors, government bodies, export councils and multinationals who want a single accountable partner for the whole participation — and the ones who find it straightforward are simply the ones who know which four decisions are theirs and when each is due.
The table below is the whole project on one screen. Read the third column first, because that is your part, and almost everything in the second column is downstream of something in the third. Timings are for a 36 sq.m standard-finish job, which the planner puts at 4 weeks — scale them up for a larger or premium build and down for a small system stall.
| Stage | What we do | What you do | How long |
|---|---|---|---|
| 1. Brief | Take the brief on a call, then write it back to you as a written scope so nothing is ambiguous | Share event, dates, area, open sides, goal, budget band and two or three references | Day 0 |
| 2. Concept | Produce the first layout, elevations and a visual from the aisle | Read the plan before the picture, and check it against the one thing you came to do | 2 days |
| 3. Revisions | Work through two rounds of changes on plan, finish, graphics and lighting | Nominate one owner for the file and send one set of comments, not five | 4 days |
| 4. Design freeze and quote | Convert the approved design into drawings, a finish schedule and an itemised figure | Check the quote against the drawings, approve in writing, raise the order | 2 days |
| 5. Organiser submission | Submit dimensions, height, loads and fire-retardancy certification for approval | Send the allotment paperwork and anything the organiser has emailed you | 3 days |
| 6. Production | Run the cutting list, finishing, printing and electricals through the workshop | Supply print-ready artwork and final content; stop changing the design | 11 days |
| 7. Pre-assembly and dispatch | Trial-fit graphics, run the electricals, pack spares and book the inward slot | Give us a name and number at the venue, and a plan for your products | 2 days, then 2 in transit |
| 8. Build-up and handover | Install to drawing, test power and lighting, clean, then walk you through the stand | Have a decision-maker reachable on the phone through build-up | 2 days |
| 9. Show days | Keep a supervisor reachable for repairs, replacements and anything the hall does to you | Staff the stand, and tell us early if anything on it needs to change | Show duration |
| 10. Dismantle | Strike the stand, clear the space inside the organiser's window, return reusables to storage | Remove products, samples, laptops and valuables before strike begins | Same night, usually |
Timings are the days each stage owns on the critical path of a 36 sq.m standard-finish build. Lead time scales with area and finish: 3 weeks base, +1 from 24 sq.m, +2 from 54 sq.m, +2 for a premium finish and +2 for a double-decker.
The schedule is soft at the front and concrete at the back. Spend your delays early, where they are free.
The ten stages, from your side of the table
Below, each stage in the detail a first-time exhibitor actually needs: what arrives, what to look at, what to say, and what it costs to be slow. Read them as a chain rather than a list — none of them can start until its predecessor is genuinely complete, which is why a fortnight of indecision early is a fortnight of night shifts late.
Pay attention to the consequence sentence at the end of each one. The stages differ enormously in how much lateness they can absorb, and knowing which is which is most of what experienced exhibitors know that first-timers do not.
01
1. The brief — the only stage that is free to get wrong
First contact is a conversation, not a form. The questions are always the same — which show, which city, which dates, how many square metres, how many sides open, what the height limit is, roughly what you intend to spend, and what a successful visit looks like — and the answers come back to you in writing before anything is drawn. Treat the gaps honestly: an unanswered question costs a sentence, an invented answer costs a redesign. Delay at this point is the only delay in the whole sequence that costs you nothing at all.
02
2. The concept — circulation first, finish later
Expect a layout, elevations and a visual from the aisle — the view a visitor actually has, not an impossible corner angle — inside 2 days. The test to apply is behavioural: does the plan make the one thing you came to do easy? A participation plan where every touchpoint, from the pavilion entrance to the VIP lounge, is designed to move visitors toward a meeting is the brief this concept is answering, and a design that photographs well while failing that test is the most expensive kind of success. Changes cost nothing at this stage and a great deal three weeks later, so this is the moment to be difficult.
03
3. Revisions — where schedules quietly break
Two rounds is almost always enough when the comments arrive together, and almost never enough when they arrive one person at a time, because round two then contradicts round one and the third round nobody budgeted for becomes unavoidable. Nominate one person to own the file, let everyone comment into it, and send it once. Be specific about what is wrong rather than what you would prefer: "the counter blocks the sightline from the main aisle" is actionable, "make it more premium" is not. The 4 days allowed here start eating into production if they overrun, and production is the one stage that cannot be shortened invisibly.
04
4. Sign-off — the point where the drawing becomes the contract
Sign-off is where intent becomes obligation, so it is worth slowing down for an afternoon. What you are approving is the drawing set and the materials schedule — the render is the sales tool, the drawing is the thing anyone can later be held to. The quote should be itemised to the point where you could delete a line and know exactly what you had given up. Confirm in writing, raise the order, and note that the 2 days booked for this stage assume your approvers are available, which is a question worth asking them in advance.
05
5. Approvals — the stage with someone else's deadline
Every show publishes an exhibitor manual containing a rulebook and a set of submission deadlines: stand drawings, dimensions and height, structural calculations for anything raised or hanging, electrical load, fire-retardancy certificates for the materials, and for a two-storey build a structural engineer's sign-off. We prepare and file all of it. What we need from you is the allotment letter, the manual itself and any organiser portal login. The risk being managed here is inconsistent branding across co-exhibitor booths. Submit late and approval can land during build-up, which means building something simpler than you approved.
06
6. Production — cutting list, print schedule, finishing
The workshop owns 11 of the 28 days on a 36 sq.m standard-finish job, and almost none of them are elastic. Material and print orders go out together on day one so that nothing waits behind one supplier. Spray and PU finishes need a cure cycle, which is the mechanical reason a premium build adds 2 weeks rather than a commercial one. Your only task in this window is artwork, and it is urgent rather than important-later: print is scheduled last, so late files land on the single most visible element of the finished stand.
07
7. The dry build — finding problems where they are cheap
Before anything is loaded, the stand is stood up in the workshop: panels numbered, graphics trial-fitted, circuits loaded and tested, lamps aimed, finishes inspected against the schedule. Problems get found here, where there is time and a paint booth, rather than on a hall floor with four hours of build-up left. Spares travel with the crew — laminate offcuts, a duplicate graphic panel, extra lamps and drivers. Then it is loaded against a packing list and dispatched, allowing 2 days in transit for an inter-city move. We need your site contact, the organiser's delivery slot, and a decision on where products will be stored.
08
8. Installation inside the organiser's hours
Build-up is shared with every other exhibitor in the hall and their forklifts, so it is a question of sequence rather than effort: floor, structure, graphics, electricals, AV, furniture, clean. Lighting is aimed at the product rather than at the floor, circuits are tested under load, and anything with a cue is run end to end before anyone goes home. The handover is a walkthrough on the stand, not a note — and it is the moment to say "that counter is on the wrong side" while a crew is still in the building and the tools are still out.
09
9. Show days — running repairs and early warnings
A supervisor stays reachable through show hours for the things that genuinely happen: a lamp fails, a graphic panel gets scuffed, a counter needs moving because the queue is forming on the wrong side, the hall's power trips. Tell us early in the day rather than at closing time. This is also where your own preparation decides the result, because the stand can create an opportunity and only a person can convert it. Brief your team on how to qualify a visitor inside the first thirty seconds — that one habit does more for the outcome than any element of the build.
10
10. Dismantle, and what comes back to you
Dismantle is part of the scope, not an afterthought, and it is worth confirming that in the quote because it is one of the lines most often absent. Practically: valuables off the stand before panels move, a crew that strikes in reverse order of the build, and clearance completed inside the organiser's charged window so no penalty touches your deposit. What you should receive afterwards is an inventory — frames, lighting, furniture, fabric graphics — because reuse is the single largest lever on cost per show, and it depends on knowing what you own.
Your four jobs, and the paperwork behind them
None of these items is hard to find. They are simply scattered: brand files in one department, the organiser's paperwork in another, product weights with the people who ship them, and the budget with someone who has not been told the brief is going out this week. Collecting them in one sitting is the single highest-return hour in the whole project.
For an event management company scope these are the non-negotiables. Anything not on the list can wait for the concept, and most of it should — reacting to a drawing is far easier than specifying in the abstract.
- The show or event calendar you are planning for, with dates and cities
- Stall or venue area per event and the audience you expect at each
- Brand guidelines and an honest list of assets that already exist and can be reused
- The list of co-exhibitors, departments or approvers whose sign-off is needed
- Who raises the purchase order, and what your procurement process needs to see
- What post-show reporting you need, in what format and for whom
| What you supply | Due by | What stalls without it |
|---|---|---|
| Event, city, dates, area, open sides and height limit | The brief | Everything. These are the numbers the design is a solution to |
| Your goal, in one sentence with a number in it | The brief | The plan optimises for looking finished rather than for working |
| Budget band | The brief | You get a concept that cannot be built for the money, and lose a week |
| Products, with weights and power requirements | The brief | Plinths and sockets get sized by assumption, and corrected on site |
| Written approval and purchase order | Design freeze | Nothing is reserved — not the materials, not the slot, not the crew |
| Print-ready artwork at final size | Start of production | Print slides to the end of the window, where there is no recovery time |
| Final content, video and presentation files | Start of production | The first full run happens in front of an audience instead of in a prep bay |
| Height, rigging and material restrictions from the manual | Before design freeze | The drawing is rejected and the fallback is a plainer stand |
| Site contact and delivery slot | Dispatch | Freight arrives outside the inward window and queues |
| Products, stock and samples on site | Handover | The stand is finished but empty when doors open |
If an item genuinely does not exist yet, say so and have it marked open. A recorded gap is manageable; an assumed answer is the thing that gets built.
What you are actually signing off
The most expensive misunderstanding in this business is approving a picture and expecting a building. A render is a sales tool and a good one; it is also lit by lamps the hall does not own, viewed from a corner nobody can stand in, and surfaced with textures that are not yet a named material. What binds is the drawing set and the finish schedule.
Spend the time on the finish schedule rather than on the render. Named codes for laminate, paint, fabric and acrylic are what make "as approved" a verifiable claim, and they cost nothing to ask for at this stage.
- The dated schedule with a named owner against each element
- The design and finish standard that applies across every booth or zone
- The close-out terms — dismantle window, deposit release and post-show reporting
- The co-exhibitor package, and which parts of it are fixed rather than optional
- The storage inventory format you will receive after the show
Where the 28 days go
The breakdown matters because it shows where the slack is. Production, approvals, freight and installation together are fixed; the front 8 days of concept, feedback and freeze are not. Exhibitors who think of the lead time as "the build" tend to spend the elastic part first and then ask for the inelastic part to be shortened.
The figures below sum to 4 weeks exactly, which is what the planner gives for 36 sq.m. These are the days each stage owns when nothing overlaps. In practice the organiser submission runs alongside production wherever the show's deadlines allow, and that overlap is your entire buffer — spend it on a late sign-off and it is gone.
| Brief call to first concept and visual | ₹2 days |
|---|---|
| Two rounds of consolidated changes | ₹4 days |
| Design freeze, materials schedule and itemised quote | ₹2 days |
| Organiser drawings prepared, submitted and cleared | ₹3 days |
| Workshop production, finishing and printing | ₹11 days |
| Pre-assembly, electrical test and dispatch | ₹2 days |
| Transport to the venue | ₹2 days |
| Installation, testing, clean and walkthrough | ₹2 days |
| Calendar days from brief to doors open | ₹28 days |
That is 4 weeks, matching the planner exactly — 3 base and 1 more from 24 sq.m. A premium finish adds 2 weeks for curing, a second storey adds 2 for engineering and approval, and an out-of-city venue adds transit. None of those are padding.
Exhibiting soon? Let's build your stall.
What the stand has to physically do, and whether it can
There is a sanity check most exhibitors skip, and it is pure arithmetic. A stall is not all display: storage takes 10% of the area up to 18 sq.m and 15% above that, and a meeting corner takes 5% by default or 20% if meetings are a stated goal. What is left is what visitors can stand in.
The numbers to run are simple. Display ÷ 2.5 gives the visitors who can physically stand in the stand at once — 11 at 36 sq.m — and area ÷ 9 gives the staff on duty, 4 at that size. The useful outcome of this check is negative: it tells you when the stall, not the stand design, is the limiting factor, at the one moment when taking more space is still possible.
| Area booked | Usable display | Storage taken | Staff needed | Visitors at a time | Build weeks |
|---|---|---|---|---|---|
| 12 sq.m | 10.2 sq.m | 1.2 sq.m | 2 | 4 | 3 weeks |
| 18 sq.m | 15.3 sq.m | 1.8 sq.m | 2 | 6 | 3 weeks |
| 24 sq.m | 19.2 sq.m | 3.6 sq.m | 3 | 7 | 4 weeks |
| 54 sq.m | 43.2 sq.m | 8.1 sq.m | 6 | 17 | 5 weeks |
| 72 sq.m | 57.6 sq.m | 10.8 sq.m | 8 | 23 | 5 weeks |
| 100 sq.m | 80 sq.m | 15 sq.m | 12 | 32 | 5 weeks |
Same arithmetic as our stall planner. Staff = area ÷ 9, minimum 2. Visitors = display ÷ 2.5, minimum 3. Lead time excludes the premium and double-decker additions.
What to do when you have already lost a week
Delay is not a failure, it is a fact of exhibition projects, and the useful question is not how to avoid it but where to put it. The schedule has soft days and hard days, and they are not distributed the way people assume — the expensive ones are at the end, long after the design decisions everyone worries about.
This is the recovery table. It is worth reading at the start of a project rather than in the middle of one, because most of the rescues listed only work if they are chosen a few days early instead of discovered on build-up morning.
| What slips | What it pushes | What you can still save |
|---|---|---|
| The brief | Nothing yet | Everything — this is the only free delay in the project |
| Feedback on the concept | Every stage after it, day for day | Drop a round and accept the second drawing |
| Internal agreement between stakeholders | The revision rounds | Give one person the final word in writing |
| Design freeze and purchase order | Organiser submission and material ordering | Freeze the structure, keep graphics open for two more days |
| Print-ready artwork | Printing, which runs last in production | Print fewer, larger panels; leave secondary graphics for site application |
| Your own staff briefing | Nothing physical — but the result | Run it in the hotel the night before; thirty minutes is enough |
| Products arriving on site | Nothing we control | Nothing — the stand will be finished and empty at opening |
| Clearing the stand at dismantle | The organiser's window, which is charged | Accept the charge and keep the crew working through it |
Every rescue in the last column has to be chosen deliberately, and most of them stop being available within a day or two of the slip.
Tell your supplier you are late on the day you know. Three answers today, one answer next week.
The three failures worth designing around
The failures worth knowing about are process failures, not design failures. Too many vendors with no single point of accountability. That is a procurement question rather than a creative one, and the way to settle it is to ask who physically does the work, in whose workshop, with which crew — before you compare prices.
Then there is the comparison problem. Unless both quotes name the finish, the number of light fittings, the flooring and the dismantle, you are not comparing suppliers — you are comparing assumptions. Itemisation is the only fix, and it has to be asked for before the prices arrive.
The third failure is ownership. Ten stages with four different parties involved and no single person watching the handovers is how a 4-week schedule ends up compressed into a weekend. The remedy is contractual, not personal: a named project manager and a dated schedule, agreed before the order rather than after it.
- Inconsistent branding across co-exhibitor booths
- Delayed approvals that compress build-up time
- Budget overruns from scope that was never itemised
- Too many vendors with no single point of accountability
Start an event management company project
To begin, we need the show and city, the build-up and show dates, your area and open sides, and two or three images with a line on what you liked about each. From that comes a concept and a line-by-line quote, usually within 48 hours, plus a frank view on whether the remaining time is enough.
Quoted per event after a brief; we share a line-item budget before you commit. We design free with every confirmed fabrication order, build in our own workshops, prepare and file the organiser drawings, and put one named project manager on the job from the first call through to clearing the stand.
- On-ground crew and show-calling
- Concept, budget and run-of-show planning
- Stage, AV, lighting and decor in-house
- Venue scouting and permissions
Frequently asked questions
How long does an event management company project take from brief to handover?+
The formula is 3 weeks base, plus 1 from 24 sq.m, plus 2 from 54 sq.m, plus 2 for a premium finish and 2 for a second storey. So 4 weeks at 36 sq.m and up to 9 weeks for a large premium double-decker. Work backwards from build-up rather than forwards from today.
How many revision rounds are included?+
Two, which is almost always enough when the comments arrive together. Nominate one person to consolidate every stakeholder's feedback into a single reply per round — serial feedback from five people is the most common reason a third round becomes necessary.
Who handles the organiser drawings and approvals?+
Your supplier should, and it should be in the scope rather than an extra. The pack is drawings, overall dimensions and height, load calculations for anything raised or suspended, the electrical load, and certification that the panel materials are fire-retardant. Send the exhibitor manual across with the brief, because its rules decide what can be drawn at all.
Is someone on site during the show?+
Yes. A supervisor stays reachable through show hours for lamp failures, scuffed graphics, counters that need moving and hall power issues. Report problems early in the day rather than at closing time.
Is dismantle included, and what comes back to me?+
Dismantle and clearing the stand inside the organiser's window are part of the scope — confirm that in the quote, because it is one of the lines most often left out. Reusable elements such as modular frames, lighting, furniture and fabric graphics go back to storage. Ask for that inventory in writing; it is what makes the next show cheaper.
Can you work to a shorter timeline than this?+
Sometimes, and always by trading something explicit. The four levers are fewer revision rounds, a simpler structure, finishes with no curing time, and paid out-of-hours labour at the venue. What cannot be done is compressing the workshop, the organiser's approval or the build-up window, so a date that depends on any of those is a date that will move.
What does the first event management company conversation cover?+
Enough to draw against: the show and city, the build-up and show dates, your area and the number of open sides, the organiser's height limit, a budget range, and the single action the event management company scope has to produce. Anything genuinely undecided is recorded as open rather than guessed at.
Do I need to be at the venue during build-up?+
Reachable is essential; present is better. Judgement calls arise in every build — a graphic that reads badly from the actual aisle, a counter on the wrong side of the queue that forms — and if nobody from your side can decide, each one defaults to the drawing. Come for the handover at minimum.
How much of my own time will this take?+
Less than exhibitors expect, and it is front-loaded: a twenty-minute brief call, an hour reading the concept, one consolidated feedback session per round, an afternoon checking the quote against the drawings, then artwork and a handover. The hours that get wasted are the ones spent re-briefing because the first brief was incomplete.